Project: Merrick & Bellmore Direct Fixation Fastener Replacement Project
Rail Operator: Long Island Railroad (LIRR)
NEW TRACK CONSTRUCTION
This project demonstrates the abilities of the CMGC Team as a design build partner.
Dates of Construction: 2012
Location:
Rail Operator: Long Island Railroad (LIRR)
Designer: Parsons Brinckerhoff (PB)
Overall Project Scope:
Project Manager: Linda Laurello
Description: The scope of the work of this Contract primarily consisted of providing the design, materials and installation of 7,832 new direct fixation fasteners on track 1 and track 2 of the 2149/2301 LIRR DF Fastener Merrick and Bellmore viaducts.
The project included the purchase of direct fixation rail fasteners, enlargement or repair and/or replacement of concrete running rail plinths, and some viaduct concrete deck repairs ranging from patching to full depth replacement.